References - THERMO ENERGETIC
PERGAMENT Bjelopolje
Water heating boiler Q=1,63MW Reconstruction instr.: M.O.R.H.
Servicing of the I&C equipment and burners in boiler-room ĐURO ĐAKOVIĆ
Making a part of the project documentation, UJPEST power plant CCPP TE-TO Zagreb
Utilization boilers TE PLOMIN II, Plomin Thermo-energetic plant 210MW
I&C delivery and service, service of the oil-burning system CCPP TE-TO Zagreb
Utilization boilers |
PTE Zagreb - west
Utilization boilers, Reconstruction instr. PALMA Jastrebarsko
Making of the project documentation, equipment delivery, mounting and commissioning of the system for temperature registration at the boiler-room exit. ENERGO Sisak
Boiler 100 t/h, Reconstruction instr. SAVA PROMET Dugo Selo
Water heating boiler Q=1,0MW, dry-kiln 2x50m3 TOPLANA PRIJEDOR
Making of the project documentation of the control system |
Đ. Đ. KOTLOVI d.o.o.
- Making a part of the project documentation, making and delivery of the control cubicles and boilers automatics
- Boiler for rapid steam production VPS 600kg/h 8 bar for the paper factory GALEB in Rijeka, making of the project documentation, equipment delivery, mounting and commissioning of the boiler-room container
- Boiler for rapid steam production VPS 1000kg/h 8 bar KUNIS Zupanja, making of the project documentation, equipment delivery, mounting and commissioning of the boiler-room container
- Thermal oil heater VKS 600 INA MAZIVA Zagreb making of the project documentation, equipment delivery, making of the boiler cubicle and mounting of equipment on the boiler
- Boiler for rapid steam production VPX 750kg/h 8 bar ALFATERM Mostar-BiH, making of the project documentation, equipment delivery, making of the boiler cubicle and mounting of equipment on the boiler
- Thermal oil heater-room with a steam generator AGROPRERADA Ivanic Grad, making of the main and final project, making of the boiler cubicle and mounting of equipment on the boiler
- Thermal oil heater VK 2000 AD NOVOTEKS Trebinje-BiH, making of the project documentation, equipment delivery, making of the boiler cubicle and mounting of equipment on the boiler
- Thermal oil heater VK 600 Gracanica-BiH, making of the project documentation, equipment delivery, making of the boiler cubicle and mounting of equipment on the boiler
- Thermal oil heater-room with a steam generator, Ucenicki dom graditeljskih struka Zagreb, making of the final project, equipment delivery, mounting and commissioning of the boiler-room
- Thermal oil heater VKS 600 Iran - customer PECON, making of the final project, equipment delivery, mounting and commissioning
- Steam boiler-room with a boiler VPK 1500 IGM Slavonija Nasice, making of the final project, equipment delivery, mounting and commissioning of the boiler-room
- Steam boiler-room with a boiler VPK 1500 Tvornica opeke Sarajevo, making of the final project, equipment delivery, mounting and commissioning of the boiler-room
- Thermal oil heater VKS 750 Rusija - customer PECON, making of the final project, equipment delivery, mounting and testing
- Steam boiler-room with 2 boilers VPS 2000 PPK Karlovac, making of the final project, equipment delivery, mounting and commissioning of the boiler-room
- Steam boiler-room with a boiler VPS 1000 COSMOS Sarajevo, making of the final project, equipment delivery, mounting and commissioning of the boiler-room
- Steam boiler-room with a boiler VPS 1500 Franck Hercegovac, making of the final project, equipment delivery, mounting
- Steam boiler-room with a boiler VPS 1500 MTT TEKSTIL Maribor, making of the final project, equipment delivery, mounting
- Steam boiler-room with a boiler VPS 2000 EUROBRAHAJ UKES Albanija, making of the final project, equipment delivery, mounting